Resource management is the process of planning the use of your resources and scheduling out their allocation. Resources can be anything your business needs in order to operate effectively— employees, equipment, or even your brand assets. Whatever your resources may be, monday.com is here to help you keep your business on track!
Before you start
To measure the workload of your team members, you'll want to make sure your boards contains the following columns:
- A People Column
- A Date or a Timeline Column
- Optional - A Number or Formula Column to indicate effort required for each task; i.e. 1 hour, 6 hours
Alternatively, if you want to measure any other resources, such as meeting rooms, factory machines, hand tools, cameras - you name it - you can use a Status Column!
Another important setting to consider is the weekend. You can either count the weekends as working days or exclude them from the working days. You can customize this setting in the admin section of your account. Check out this article to learn more.
How to add the view to your board
To add the Workload View to your board, click on the option at the top of your board (it will say "Add View" when you hover over it). Select "More views" and search for "Workload" in the Views Center:
You can also add a new board view by clicking on "Board Power-Ups" in the upper right corner of your screen. Select "Board Views" and choose "Workload" from the Views Center:
How to add the widget to your Dashboard
To add the Workload View widget to your Dashboard or Dashboard View, click on "+ Add widget" and select "Workload":
Setting up the view
Step 1 - Build your board
Let's say we are managing our Customer Success Team. In our board, we have:
- A People Column to assign each task to one or more team members
- A Timeline or Date Column to define the time frame of the task
- Optional - A Numbers Column that we are using as a time estimation for each task.
Step 2 - Choose the time column
Since this view checks all items assigned to a person over a certain time period, your board must have either a Date or Timeline Column.
Step 3 - Choose the resource type
Now you need to choose which resource type you want to be represented on the workload. The resource type can be a People Column, Status Column, or group. This will determine according to what parameters we see the workload divided.
Step 4 - Measure the effort
You can display the data in two ways: count item and effort.
- Count Item
If you choose Count items, each item that is assigned to that person will be counted as 1 and displayed on the board.
- Effort
Sometimes, some of our tasks take more effort or carry more weight to the project. In our use case, we are using the time estimation column. That setting works with both a numbers or formula column.
When more than one person is working on a task, we can choose to display how they "divide the effort" between them. We can toggle between "Split", which will divide the effort equally amongst partners, and "Sum", which will assign each of the partners the total number of hours that the project takes.
- Weekly Capacity
Once done, we can then choose a Weekly Capacity for the entire team. This will be the limit of how many hours you want the team to be working on those tasks in that week. In our example, we set up the week capacity to 20 hours per week.
Allocating Resources
With the Workload, you can allocate people but also any resources. In the example below, we want to make sure that none of our vehicles are surpassing their weekly limit of 1200 total kilometers of travel distance. We can set our Workload View to show us exactly that!
First, we select our "Vehicle" Status Column as our resource type, and then we can select "Add Effort"! We want to define our effort by our "Travel Distance" Numbers Column, and then enter "1200" in the "Weekly Capacity" field below.
Now, our view is showing us all of our vehicles listed in the left panel, and to their right, we can see how many kilometers they are scheduled to travel each day of the week. We can see that our Ford is set to exceed its limit on the 13th, so we can go ahead and schedule a different vehicle for this delivery instead!
Understanding the colors
🔵 Blue Bubble - The person is below the maximum amount of effort. You can keep assigning tasks!
✔️Blue Bubble with a check mark - You are right at the weekly capacity!
🔴 Red Bubble - The person has gone over the Weekly Capacity limit that was set
You can view the team's workload by Days, Weeks, or Months.
Understanding the results
Let's go back to our customer success board example. Here, Lea has been assigned to two tasks, each of them taking 1.5 hours.
To understand the results, we need to look at two factors:
- How many hours it takes to complete the task
- How many days we have to complete it.
Let's go back to our board:
In this example, recording a video takes 4 hours of work and needs to be completed within 8 working days excluding the weekends. This means that every day, we will need to put 0.5 hours of work toward this task. This is just a simple math equation:
Drill down for more details
If you want to have a closer look at the team's tasks, you can click on any of the circles and see the tasks listed on that timeframe.
If you have any questions, please reach out to our team by using our contact form. We're available 24/7 and happy to help!